TL;DR
How long does it take to build a custom house in Metro Vancouver? A realistic 18 to 24 month timeline covering pre-construction and build phases.
Plan on a short run of pre-construction steps, then 8 to 12 months of construction. The first call and site visit take about 2 weeks, pricing takes another 1 to 2 weeks, and design takes 4 to 6 weeks. Permits take 3 weeks to 10 or more, and no one controls that stage. This is how long it takes to build a custom house in Metro Vancouver.


What Happens Before Construction Starts?
The early stages are short, but they run in a fixed order. This is the sequence David Bond, CoreVal's President, describes:
- First call and site visit: about 2 weeks. You speak directly with Gordie, the owner, and within minutes you are looking at your property and what is possible. The site visit covers your vision, your budget and your needs.
- Rough numbers and discussion: 1 to 2 weeks of internal discussion and back and forth with you.
- Design and revisions: 4 to 6 weeks, sometimes with specialists brought in.
- Permits: 3 weeks to 10 or more.
While the permit is under review, your builder should be planning the build and finalizing details. That keeps the start of construction from slipping once approval arrives.
Use the low and high ends of every stage when you plan your rental, your kids' school year and your cash flow. A single date for the whole run is a guess.


Why Do Permits Take so Long?
"Permits... that's the part everyone underestimates," says David Bond, CoreVal's President. "It can be 3 weeks, it can be 10+, and you don't fully control it."
Each Metro Vancouver municipality runs permits at its own pace and to its own checklist. Burnaby, Coquitlam and the City of Vancouver all differ, so a timeline that is honest for one city can be wrong for the next.
Energy rules shape the drawings too. The BC Building Code has required Step 3 of the BC Energy Step Code for new homes province-wide since May 1, 2023, and some municipalities ask for more. The City of Vancouver's Building By-law aligned with EL-4 of the BC Zero Carbon Step Code on March 1, 2025, for new 1 to 3 storey homes on the performance path. Designing for these rules from the start avoids resubmissions that add weeks.
You cannot speed up a city's review. You can ask your builder what the current wait is in your municipality and what they are doing during it.


How Long Does Construction Take, and Why Does the End Drag?
Construction usually runs 8 to 12 months. Soil, foundations, civil work and utilities are the real variables, because you cannot see them on drawings.
David Bond gives an example: "We had a project where we started digging and found 8-foot boulders all around the house. You don't see that on drawings. It's like a blood test; sometimes it reveals something that was impossible to know before." A calendar needs room for surprises like that, and a budget does too. In his words, a builder who tries to hit a number perfectly and never prepares you for hidden conditions is not doing the job properly.
The end of the job is where people lose patience. "The last 5% feels like the longest," David Bond says. "Everyone thinks it's basically done, but there's still a lot of coordination, drying time, inspections. It can feel like the site went quiet for a few days and people get nervous."
CoreVal answers that with communication. It keeps chat groups with clients and replies quickly, so a quiet site never leaves you guessing. A good builder also will not rush finishes, fixtures, the punch list or final inspection because a calendar date says the job should be done.
How Can You Tell If a Builder's Timeline Is Honest?
A timeline is only as good as the system behind it. David Bond's view is that custom building is complex but controllable: "If you have a system, real organization, and you actually follow a process, you eliminate most of the chaos." He believes much of the unpredictability people blame comes from poor planning and weak systems, and that a solid backend should make the whole business run more smoothly than it does.
Use this checklist before you sign:
- Ask for a milestone calendar instead of a lone move-in date. Each milestone should show what it depends on, such as permit approval or inspections.
- Look for ranges where the builder cannot know. A builder who promises one exact permit date is guessing, because permits are the stage no one controls.
- Meet the actual people. Sit down with management and the project manager. Ask to speak with clients who are going through a build right now, and skip anyone who left a review 10 years ago.
- Walk a job site. David Bond says you learn more in 10 minutes on site than in hours of meetings.
- Check the licence. BC builders must be licensed through BC Housing's Licensing and Consumer Services, and the registry takes a minute to search.
- Ask how they handle surprises. Contingencies should be built in and discussed upfront.
Do not choose on kitchen photos alone. David Bond points out that any good builder working with a designer can produce a beautiful kitchen. The real question is whether they can deliver your vision, your experience and your expectations on a schedule they can explain.
Here is a quick test for any builder's answer. Write down each phase they quote, with its low and high ends, and add the lows together and the highs together. Compare both totals with the move-in date they promise. If the date sits outside that range, ask which stage they expect to compress, and why.
If you are ready to start, CoreVal's custom home build service page covers the next steps. For a second dwelling on your lot, see the laneway homes page.